Huaisheng Section

Site Location The redevelopment site is located on the southwest portion of a fragmented block in Da’an District, Taipei City. The block is bounded by Section 1 of Fuxing South Road (west), Section 3 of Zhongxiao East Road (north), Antong Street (east), and Lane 126 of Fuxing South Road (south). Planning Coverage Covers 19 land parcels, including Parcel No. 121-4 in Subsection 1 of the Huaisheng Section. Designation Officially designated as an urban renewal unit by Taipei City Government on November 7, 2008, with portions overlapping the “Da’an-1 Civic Boulevard Axis (Xinsheng Section) Renewal Area” announced on December 10, 2018. Total Site Area Approximately 911 square meters (275.58 ping). Land Tenure Mixed ownership – includes privately held land and public assets (national and municipal). Zoning Breakdown *Special Commercial Zone 3 (re-zoned from Commercial Zone 2)
*Special Commercial Zone 3 (re-zoned from Residential Zone 3)
*Road reserve
Development Approach Rights conversion through joint submission of development rights and obligations Lead Developer Delpha Construction Co., Ltd. Urban Renewal Facilitator Guanlin Real Estate Advisory Co., Ltd. Design Consultant Hsiao Li-Jen Architects & Associates and Robin Architects Project Milestones 2008.11.07 Urban Renewal Unit officially designated
2018.12.10 Included in Da’an-1 Civic Boulevard Redevelopment Corridor
2020.01.03 Community hearing (developer-led)
2020.04.08 Submission of business and rights conversion plans
2020.08.07 First public display initiated
2020.08.27 First formal public hearing (government-facilitated)
2021.09.03 Second round of public display
2021.09.15 Second government-hosted public hearing
2022.03.03 Internal review and rights conversion task force meeting
2022.10.13 Task force second review session
2023.02.08 Posting of review committee version of project report
2023.08.17 Official public hearing held
2023.09.18 First Review Committee convened
2023.11.30 Report version for second review posted
2024.08.12 Second Review Committee meeting conducted
2024.09.03 Minutes of public sector meeting distributed
2024.09.27 Approved final report posted
2025.03.25 Final review by Urban Regeneration Office
2025.03.27 Signed by Urban Development Dept. and Mayor’s Office
2025.04.10 Official government approval letter issued
Current Status & Forward Outlook *City government approval secured
*building permit currently under review