Youthful Mansion
-
12
2023
-
2023/12 Groundbreaking ceremony -
2023/12 Groundbreaking ceremony
-
-
01
2024
-
2024/01 Intermediate platform wharf pile nail installation -
2024/01 Peripheral H-shaped steel construction
-
-
02
2024
-
2024/02 The first excavation, the current situation of the base, poles and surrounding areas -
2024/02 Pressure beam steel binding formwork assembly -
2024/02 Pressure beam steel binding formwork assembly -
2024/02 Rail pile pressure beam construction
-
-
03
2024
-
2024/03 The second dig was unearthed -
2024/03 The second dig was unearthed -
2024/03 Installation of supports - first support platform and horizontal support construction -
2024/03 Installation of supports - first support platform and horizontal support construction -
2024/03 Installation of supports - first support platform and horizontal support construction -
2024/03 Installation of supports - first support platform and horizontal support construction
-
-
04
2024
-
2024/04 Styrofoam mortar -
2024/04 Installation support - second support horizontal support installation and back filling -
2024/04 Installation support - second support horizontal support installation and back filling -
2024/04 Installation support - second support horizontal support installation and back filling -
2024/04 Installation support - second support horizontal support installation and back filling -
2024/04 Installation support - second support horizontal support installation and back filling -
2024/04 safety support -
2024/04 Construction of platform railings
-
-
05
2024
-
2024/05 Construction of strong waterstop around B3F -
2024/05 B3FL opening anti-falling device -
2024/05 B3FL floor pink finish -
2024/05 B3FL stakeout inspection -
2024/05 B3FL Floor Slab Flatness Elevator -
2024/05 B3FL floor grouting -
2024/05 B3FL concrete specimen -
2024/05 B3FL grouting grouting spread degree inspection -
2024/05 B3FL sprinkler maintenance -
2024/05 B3F basic version steel bar binding -
2024/05 B3F basic version steel bar binding -
2024/05 B3F elevator shaft net length and width inspection -
2024/05 B3F elevator shaft net length and width inspection -
2024/05 BS version steel bar binding
-
-
06
2024
-
2024/06 B2FL beam reinforcement binding -
2024/06 B2FL formwork beam assembly -
2024/06 B2FL formwork beam assembly -
2024/06 B2FL formwork beam assembly -
2024/06 B2FL formwork beam assembly -
2024/06 B2FL formwork beam assembly -
2024/06 B2FL layout water and electricity laying out piping -
2024/06 B3F column wall beam plate formwork assembly -
2024/06 B3F column wall beam version steel bar binding -
2024/06 B3F Water and electricity construction -
2024/06 B3F Water and electricity construction -
2024/06 B3F steel bar extension -
2024/06 B3F opening railing setting -
2024/06 The second support is removed
-
-
07
2024
-
2024/07 Installation of B1FL floor leveling and elevation device -
2024/07 B1FL grouting -
2024/07 B2FL opening railing installation -
2024/07 B2FL opening railing installation -
2024/07 B2F template half wall assembly -
2024/07 B2F template half wall assembly
-
-
08
2024
-
2024/08 B1FL stakeout -
2024/08 B1F half wall template assembly -
2024/08 B1F half wall template assembly -
2024/08 B1F half wall template assembly
-
-
09
2024
-
2024/09 1FL hanging formwork installation -
2024/09 1FL hanging formwork installation -
2024/09 1FL hanging formwork installation -
2024/09 1FL hanging formwork installation -
2024/09 1FL hanging formwork installation -
2024/09 1FL hanging formwork installation -
2024/09 1FL hanging formwork installation -
2024/09 1FL column reinforcement protection before grouting -
2024/09 1FL column reinforcement protection before grouting -
2024/09 1FL steel bar binding beam version -
2024/09 1FL steel bar binding beam version -
2024/09 1FL steel bar binding beam version -
2024/09 1FL steel bar binding beam version
-
-
10
2024
-
2024/10 1FL layout cleaning before pouring -
2024/10 1FL layout cleaning before pouring -
2024/10 1FL layout cleaning before pouring -
2024/10 1FL layout cleaning before pouring -
2024/10 1FL aerial photos -
2024/10 1F stakeout operation -
2024/10 1F stakeout operation -
2024/10 1F column bar torsion test -
2024/10 1F column bar torsion test -
2024/10 1F column bar torsion test -
2024/10 1F column bar torsion test -
2024/10 1F column bar torsion test -
2024/10 1F column bar torsion test -
2024/10 1F column bar torsion test -
2024/10 1F column bar continuation project -
2024/10 1F formwork beam construction -
2024/10 2FL template paving -
2024/10 2FL template paving -
2024/10 2FL template paving -
2024/10 2FL template paving -
2024/10 2FL template paving -
2024/10 2FL template paving -
2024/10 2FL aerial photo -
2024/10 2FL aerial photo
-
-
11
2024
-
2024/11 2FL beam plate formwork assembly -
2024/11 2FL beam plate formwork assembly -
2024/11 2FL beam version steel bar binding -
2024/11 2FL beam version steel bar binding -
2024/11 2FL water and electricity stakeout -
2024/11 2FL water and electricity piping -
2024/11 2FL水電配管x -
2024/11 2FL concrete placement -
2024/11 2FL concrete placement -
2024/11 2FL cleaning before grouting -
2024/11 2FL aerial photo -
2024/11 2FL aerial photo -
2024/11 2F column wall column reinforcement torsion test -
2024/11 2F column wall column reinforcement torsion test -
2024/11 2F column wall column reinforcement torsion test -
2024/11 2F column wall column reinforcement torsion test -
2024/11 2F column wall steel bar binding -
2024/11 2F column wall steel bar binding -
2024/11 2F column wall steel bar binding -
2024/11 2F column wall steel bar binding -
2024/11 2F column reinforcement continuation -
2024/11 2F column reinforcement continuation -
2024/11 2F column reinforcement continuation -
2024/11 2F column reinforcement continuation -
2024/11 2F column reinforcement continuation -
2024/11 2F column reinforcement continuation -
2024/11 2F formwork wall module installation -
2024/11 2F formwork wall module installation -
2024/11 2F formwork wall module installation -
2024/11 2F模板牆模組立4x -
2024/11 2F鷹架搭設x -
2024/11 3FL formwork beam deep inspection -
2024/11 3FL formwork beam deep inspection -
2024/11 3FL formwork beam deep inspection -
2024/11 3FL water and electricity stakeout -
2024/11 3FL water and electricity stakeout -
2024/11 3FL water and electricity stakeout -
2024/11 adding iron length)) -
2024/11 3FL steel bar binding -
2024/11 3FL steel bar binding
-
-
12
2024
-
2024/12 4FL beam version water and electricity piping -
2024/12 Aerial photos of 4FL layout and reinforced beam layout -
2024/12 Aerial photos of 4FL layout and reinforced beam layout -
2024/12 4F column wall formwork assembly -
2024/12 4F column bar torsion inspection -
2024/12 4F column bar torsion inspection -
2024/12 4F column steel bar inspection -
2024/12 4F column steel bar inspection -
2024/12 5FL formwork beam bottom assembly -
2024/12 5FL formwork beam bottom assembly -
2024/12 5FL formwork beam bottom assembly -
2024/12 5FL formwork beam bottom assembly -
2024/12 5FL formwork beam bottom assembly -
2024/12 5FL formwork beam bottom assembly -
2024/12 5FL formwork beam bottom assembly -
2024/12 5FL formwork beam bottom assembly aerial photo -
2024/12 5FL water and electricity piping -
2024/12 5FL grouting -
2024/12 5FL grouting -
2024/12 5FL grouting -
2024/12 5FL grouting -
2024/12 5FL grouting -
2024/12 5FL steel bar binding, water and electricity piping -
2024/12 5FL steel bar binding, water and electricity piping -
2024/12 5F column wall reinforcement binding -
2024/12 5F column wall reinforcement binding -
2024/12 5F column wall reinforcement binding -
2024/12 5F column wall reinforcement binding -
2024/12 5F formwork column and wall assembly
-
-
01
2025
-
2025/01 6FL beam grouting -
2025/01 3F indoor setting out -
2025/01 6F column wall assembly -
2025/01 6F column wall assembly -
2025/01 External pipe excavation work -
2025/01 6F water and electricity piping -
2025/01 7F water and electricity piping -
2025/01 Black soil on top of basement floor -
2025/01 Basement interior wall construction -
2025/01 6F column connection -
2025/01 7F column connection -
2025/01 6FL beam version steel bar binding -
2025/01 7F column reinforcement binding
-
-
02
2025
-
2025/02 8FL grouting -
2025/02 8FL grouting -
2025/02 stake out-5F indoor -
2025/02 Template-7F column wal -
2025/02 Template-8FL beam version -
2025/02 8F piping -
2025/02 Paint roof polishing-2F -
2025/02 Mud Work-B1F Mud Work -
2025/02 Mud Work-B1F Mud Work -
2025/02 Mud Work-B1F Mud Work -
2025/02 Continuation-8F column connection -
2025/02 8FL beam version lashing -
2025/02 Steel bar binding-8F column
-
-
03
2025
-
2025/03 2F aluminum window stand -
2025/03 2F aluminum window stand -
2025/03 4-5F compartment construction -
2025/03 Tamping-11FL Grouting -
2025/03 Tamping-11FL Grouting -
2025/03 Tamping-11FL Grouting -
2025/03 Tamping-11FL Grouting -
2025/03 Water and electricity-1F hanging pipe -
2025/03 Water and electricity-5F indoor wire drawing -
2025/03 Gypsum Brick-3F Compartment -
2025/03 Gypsum Brick-3F Compartment -
2025/03 Continuation-10F column connection -
2025/03 Continuation-10F column connection -
2025/03 Continuation-10F column connection -
2025/03 Steel bar tying-10F column bar tying -
2025/03 Steel bar tying-10F column bar tying -
2025/03 Steel bar tying-10F column bar tying -
2025/03 Steel bar tying-10F column bar tying -
2025/03 Waterproof-2.3F Exterior wall waterproof -
2025/03 Waterproof-B3F Peripheral Wall Seam Injection -
2025/03 Waterproof-B3F Peripheral Wall Seam Injection
-
-
04
2025
-
2025/04 12FL formwork beam assembly -
2025/04 12FL formwork beam assembly -
2025/04 13F column wall formwork assembly -
2025/04 13F column wall formwork assembly -
2025/04 2-4F compartment electrical pipe cutting and piping -
2025/04 2-4F compartment electrical pipe cutting and piping -
2025/04 250426 Base Aerial Photography -
2025/04 2F Indoor mud work -
2025/04 4F exterior wall plastering -
2025/04 6F gypsum brick -
2025/04 7-8F Compartment -
2025/04 7-8F Compartment -
2025/04 B1F roof paint and soil -
2025/04 B1F roof paint and soil -
2025/04 Formwork 12F column wall assembly -
2025/04 9F Water pipe -
2025/04 Water and electricity-13F column wall pipe box -
2025/04 Mudwork-3F exterior wall flatness self-inspection -
2025/04 Rebar Binding-13F Column Wal -
2025/04 Waterproof-2F toilet water test -
2025/04 Waterproof-2F toilet water test
-
-
05
2025
-
2025/05 11F water pipe construction -
2025/05 12-15FL water, electricity and fire fighting layout -
2025/05 15FL beam assembly -
2025/05 5FL beam assembly -
2025/05 2-3F paint finish -
2025/05 2F glass installation -
2025/05 2F ceramic tile kitchen and toilet wall tile -
2025/05 3F Two Ding Hanging -
2025/05 3F kitchen and toilet wall tiles -
2025/05 3F Test Water -
2025/05 5-15FL water, electricity and fire fighting layout -
2025/05 5F Indoor mud work -
2025/05 Partition-9F gypsum stacking brick
-
-
06
2025
-
2025/06 10F partition wall stacking bricks -
2025/06 11-12F water and electricity pipe hanging construction -
2025/06 11F exterior wall hanging wire adhesive strip -
2025/06 1F Mud Works -
2025/06 5F Test Waters -
2025/06 9-10F window work -
2025/06 9-10F partition wall water and electricity setting out -
2025/06 R1F column wall water and electricity piping test -
2025/06 R1F connection -
2025/06 Dahuayang beam raising ceremony -
2025/06 Dahuayang beam raising ceremony -
2025/06 Dahuayang beam raising ceremony
-
-
07
2025
-
2025/07 10th floor partition wall water and electricity distribution -
2025/07 11th floor window installation -
2025/07 12th floor gypsum brick -
2025/07 2nd floor sample house ceiling construction -
2025/07 4th floor bathroom tiles -
2025/07 5F tiles -
2025/07 R2F beam plate assembly -
2025/07 R2F connection -
2025/07 Window side plug water channel pre-operation
-
-
08
2025
-
2025/08 11F blocking plate construction -
2025/08 11F blocking plate construction -
2025/08 13F stacked brick -
2025/08 13F stacked brick -
2025/08 Kitchenware installation in the sample house on the 2nd floor -
2025/08 Kitchenware installation in the sample house on the 2nd floor -
2025/08 8F kitchen and toilet wall tiles finishing -
2025/08 8F kitchen and toilet wall tiles finishing -
2025/08 8F staircase floor tiles -
2025/08 8F staircase floor tiles -
2025/08 PRFL grouting -
2025/08 indoor cleaning -
2025/08 Sample house wooden door installation
-
-
09
2025
-
2025/09 10F water leakage test (2) -
2025/09 10F water leakage test -
2025/09 2FA2 model unit -
2025/09 2FA1 unit shower sliding door installation -
2025/09 1F exterior wall facing brick tile installation -
2025/09 2F stair hall small floor tile grouting -
2025/09 R1F scaffolding erection
-
-
10
2025
-
2025/10 11F Gypsum Block Putty Application (2) -
2025/10 11F Gypsum Block Putty Application -
2025/10 15F Material Hoisting -
2025/10 8–5F Brick Tile Installation -
2025/10 Taipower Power Reception Inspection -
2025/10 Exterior Wall Masonry Work -
2025/10 Inspection of 15F Slab Structure Maintenance Condition (Post-Rain Leakage Record) (2) -
2025/10 Post-Rain Leakage Record) -
2025/10 Paint Work for Viewing Path Planning -
2025/10 Showroom Kitchen Fixture Installation -
2025/10 Permanent Elevator Installation in Progress
-


