The Gorgeous Mansion
-
06
2024
-
2024/06 FS version decompression well buried
-
2024/06 Finally dug out the soil
-
-
07
2024
-
2024/07 B4F version water tank bottom plate and side wall grouting
-
-
08
2024
-
2024/08 B3F bottom plate grouting
-
-
09
2024
-
2024/09 B1F beam version assembly
-
2024/09 B2F column wall lashing
-
2024/09 B2F column wall lashing
-
2024/09 B2F version elevation device implementation
-
-
10
2024
-
2024/10 B1F beam version grouting
-
2024/10 B1F lane rack construction
-
-
01
2025
-
2025/01 1F half wall pouring
-
2025/01 1F top water and electricity stakeout
-
2025/01 1F top template assembly
-
2025/01 1F residential wall formwork assembly
-
2025/01 1F roof water and electricity piping
-
2025/01 1F roof pouring
-
2025/01 2F version of scaffolding installation
-
-
02
2025
-
2025/02 2 Floor roof water and electricity stakeout
-
2025/02 3FL grouting
-
2025/02 3rd floor wall reinforcement binding
-
2025/02 3 Floor roof slab construction
-
2025/02 3 Floor roof water and electricity stakeout
-
2025/02 3rd floor sealing double-sided mold
-
2025/02 3rd floor sealing double-sided mold
-
2025/02 3 Floor beam and slab assembly
-
-
03
2025
-
2025/03 4th floor grouting
-
2025/03 5 floor template finalization
-
2025/03 5th floor water and electricity piping
-
2025/03 5 Floor grouting column reinforcement cleaning
-
2025/03 3
-
2025/03 5 Floor column wall single-sided formwork assembly
-
2025/03 5 floor grouting
-
2025/03 6 Floor Architect Survey
-
2025/03 Stone cutting on the second underground floor
-